Facility

One plant template, 100 by 50 metres.

Each GEMCO site is laid out to the same plan: a 5,000 m² plot carrying two production halls, an engineering and prototyping centre, storage, offices and welfare space — with land deliberately held back for expansion.

Concept design

The plant, as designed

A single-storey pre-engineered steel facility on a 5,000 m² plot: two column-free production halls fed from one service yard, with engineering, offices, storage and welfare grouped opposite them.

25143678
1Production hall — Phase 1: three lines (SMT, through-hole, module and cabinet assembly)
2Production hall — Phase 2: three further lines, built on land reserved from the start
3Engineering, R&D and prototyping centre
4Offices and meeting rooms
5Climate-controlled component store and finished-goods staging
6Canteen, welfare and visitor reception
7Service yard — goods-in at one end, dispatch at the other, one-way through the plant
8Landscaped green area held for future expansion

Concept design, drawn to the plot dimensions. Teal bands on the production roofs are the skylight and rooftop-solar zones; the green plane is land held back for Phase 2. Final architecture adapts to each country's plot, codes and utility connections.

Design intent

Expandable from day one

Phase 2 is not a hope — it is drawn, serviced and left clear. The second hall lands on prepared ground without disturbing production in the first.

Design intent

Flow sets the layout

Material enters at one end of the service yard and leaves at the other. Nothing crosses back over itself, which is what keeps handling damage, mix-ups and rework down.

Design intent

One drawing, three countries

The same envelope, spans and service runs are used at each site, so equipment layouts, training material and spare-parts lists transfer unchanged.

Site plan

How the plot is used

Production — Phase 23 lines≈ 700 m²Production — Phase 13 lines≈ 700 m²Storage200 m²Offices &meeting100 m²EngineeringR&D100 m²Canteen &guest area100 m²Green area — reserved for future expansionONE-WAY MATERIAL FLOW100.00 m50.00 m
Production hallsEngineering, R&D and prototypingSupport, storage and welfare

Schematic site plan, drawn to scale. Zone positions are indicative and adapt to the plot and regulations of each country.

Schedule of areas

Every square metre accounted for

Standard zone schedule applied at each plant.
ZoneAreaPurpose
Production hall — Phase 1≈ 700 m²Three production lines: SMT assembly, through-hole, module build
Production hall — Phase 2≈ 700 m²Three further lines added as volume and product range grow
Storage200 m²Climate-controlled component storage and finished-goods staging
Engineering, R&D and prototyping100 m²Board design, prototype assembly, bring-up and test-jig development
Offices and meeting rooms100 m²Administration, planning, customer and supplier meetings
Canteen, recreation and guest area100 m²Staff welfare and visitor reception
Green area and circulationBalance of plotLandscaping, parking, yard and reserved land for future expansion
Total plot100.00 × 50.00 m5,000 m² per site

Construction and services

Built for electronics, not adapted for it

Dust, static, humidity and temperature swings decide the yield of an LED line. The building is specified around them.

Building

Shell and envelope

  • Pre-engineered steel structure — fast to erect, column-free production spans
  • Insulated sandwich panel walls and roof for thermal efficiency in Gulf summers
  • Polished concrete floor with ESD coating throughout the production area
  • Clear internal height of 3.6–4.5 m for ventilation and machine access
  • Skylights and clerestory glazing to cut daytime lighting load
  • Mezzanine-ready design so office space can grow without taking floor area
Systems

Services and controls

  • HEPA-filtered HVAC holding stable temperature and humidity for calibration work
  • ESD-controlled zones with conductive flooring and ESD-safe benches
  • Local extraction at soldering stations plus general ventilation
  • Centralised power distribution with UPS and standby generator
  • Fibre-optic backbone linking machines, inspection systems and inventory control
  • Automatic fire suppression suited to electronics, with signed escape routes
  • Rooftop solar and rainwater harvesting where the site and budget allow

Why the same plan three times. A common layout means a process proven in one plant transfers to the next without redrawing it: the same line sequence, the same test stations, the same training material, and the same spare-parts list. It also lets the three plants cover for one another on capacity and specialist equipment.