Roadmap

Oman first, then Saudi Arabia, then Syria.

The plants are built in sequence, not in parallel. Each one only starts when the previous plant's process, training material and supply chain are proven enough to copy.

Sequence

Five years, in order

2026

Ground work

Site selection and licensing in Oman, agreements with our manufacturing partners in China, equipment specification for the interactive flat panel line, and formation of the founding engineering and production team.

Oman
2027

First line in production

The Oman plant is commissioned and the interactive flat panel line enters production as SKD assembly. Equipment for the direct-view LED line is specified, ordered and installed; the engineering centre opens alongside it.

OmanPhase 1
2028

LED modules and deeper localisation

The LED video wall module line goes live in Oman on a full SMT process. Interactive panel assembly moves from SKD toward CKD. Site work and licensing begin for the Saudi plant.

OmanSaudi Arabia
2029

Second plant, and design ownership

The Saudi plant is commissioned on the same template. The first board revisions designed in our own engineering centre enter production, and the Phase 2 programme opens: robotics, unmanned aerial systems, communication devices and video conferencing.

Saudi ArabiaOmanPhase 2
2030

Third plant and in-house products

The Syria plant is commissioned, products designed in-house enter production, and Phase 2 production lines are added in the Oman facility using the land reserved for them.

SyriaOman

What moves the plan forward

Three gates, not three dates

The years below are targets. What actually releases each step is a set of conditions being met.

Gate 1

Process before volume

A line moves to higher volume only once first-pass yield, AOI results and burn-in failure rates hold steady across consecutive production runs.

Gate 2

People before product

A product moves from SKD to CKD, or from partner design to our own, only when the local team can run and troubleshoot it without outside support.

Gate 3

Proven plant before the next plant

A new country starts when the previous plant's procedures, test jigs, training material and supplier list are documented well enough to be copied.

Note. This roadmap is indicative. Dates depend on licensing, partner and equipment lead times, and site readiness in each country, and will be updated as each milestone is confirmed.